ACARP ACARP ACARP ACARP
Underground

Prestressing of Strands to Improve Cable Performance

Underground » Strata Control and Windblasts

Published: December 97Project Number: C4025

Get ReportAuthor: Peter Fuller, M Bijelac, IR Hulls, T Rochford | BFP Consultants

High load capacity cable bolts and Flexibolts have the potential to be pretensioned to relatively high loads of 30 tonnes while still allowing further roof deformation and bolt loads to increase before failure loads are reached. The benefits of pretensioning cables have been assessed in this project by an initial laboratory based testing program followed by a series of field evaluations. Results from laboratory testing of shear and opening behaviour of a single joint have shown that:

  • the resistance to joint opening increases with cable pre-tension load,
  • joint shear resistance increases by approximately the pretension load at small shear displacement but once shearing increases, the shear resistance is less dependent on the level of pretension,
  • pretension loads will be maintained if the cable anchorage length is adequate and the end fittings and plates remain relatively stiff, and
  • the stiffness of the reinforced joint to both opening and sliding is increased significantly by a cable pretensioned to 15 tonnes.

The most efficient method of pretensioning cables is to stretch the free length between an anchored portion and the cable end fitting at the hole collar using a hydraulic jack. The stretch is then taken up within the end fitting so that releasing the jack allows the majority of the jack load to be retained as pretension. A tension locker end fitting for both strand cables and Flexibolts was developed during the project and used for all field based trials.

Six field trials were completed at three collieries; West Wallsend, Newstan and Wyee. These mainly involved pretensioning long point anchored Flexibolts but at Wyee one trial was attempted with two stage fully encapsulated Flexibolts which were pretensioned after the point anchor had developed but before the secondary grout had cured. Results from the fieldwork showed that:

  • pretensioning Flexibolts to 25 tonnes can be reliably achieved provided prior roof deformation is small and within the first 2 to 3m of the roof,
  • there is no advantage in pretensioning cables if the roof has deformed to the point where the height of softening is within or above the cable anchorage horizon,
  • pretensioned Flexibolts can reduce and in some cases eliminate the time dependent creep deformation in the roof that commonly occurs between development and longwall induced stress changes, and
  • at West Wallsend, the onset of longwall induced roof deformation was delayed until the longwall was within about 8m of the trial site; this contrasts with the performance in adjacent areas reinforced with non pretensioned Flexibolts where the longwall started to affect roof movements when it was 50 - 60m away.

Experience with various Flexibolt plates and end fittings during the field trials has shown that a butterfly plate should be used with a domed plate to reduce the potential to overload point anchored Flexibolts and minimise plate punching in weak immediate roof.

 

Underground

Health and safety, productivity and environment initiatives.

Recently Completed Projects

C34019Longwall Bretby Cable Handling Monitoring With Fibre Optics

This project examined the potential of using fibre optic sensing tec...

C28028The Inclusion Of High Interest Native Plants In Mine Site Restoration Programs: Propagation, Translocation And Field Re-Introduction

This report synthesises over 10 years of ex situ and in si...

C27049Mine Machine Radar Sensor Integration

The aim of this project was to develop an integrated radar sensor an...

Underground

Open Cut

Safety, productivity and the right to operate are priorities for open cut mine research.

Recently Completed Projects

C34029Validation Of Laser Induced Breakdown Spectroscopy (LIBS) As A Rapidly Deployable Field Technology To Estimate Coal Quality

Rapid evaluation of a coal resource by in-situ characterisation dow...

C34028Guidelines For Assessment Of Geotechnically Safe And Stable Post-Mining Landforms

The purpose of this project was to develop a guidelines document as ...

C34016Elements In Coal – A Start-To-End Analysis

This project explores the fate and concentration potential of critical e...

Open Cut

Coal Preparation

Maximising throughput and yield while minimising costs and emissions.

Recently Completed Projects

C26016Determining The Benefits Of Online Thickener Underflow Rheology Measurements

The aim of this project is to determine how useful the rheology meas...

C33056Modelling And Control Of Classifying Cyclones

Hydrocyclones are one of the key technologies for the classification...

C28056Surface Alloying Of Centrifuge Baskets And Sieve Bends Screen Surfaces To Increase The Service Lifetime

The main objective of this project was to improve the wear resistanc...

Coal Preparation

Technical Market Support

Market acceptance and emphasising the advantages of Australian coals.

Recently Completed Projects

C33066Washability And Distribution Of Sulfur And Trace Elements For Different Size And Density Fractions Of Raw Coals

Based on the hypothesis that the levels of sulfur and other toxic tr...

C34060In-Situ Investigation Of Coke Structure Formation Under Stamp Charged Coking Conditions

Stamp charged cokemaking has emerged as an effective technique to im...

C34062Improving The Classification Of Microstructure Distribution In Coke CT Images Using Deep Learning And Lineal Path Calculations

This project builds on a number of earlier projects that have helped...

Technical Market Support

Mine Site Greenhouse Gas Mitigation

Mitigating greenhouse gas emissions from the production of coal.

Recently Completed Projects

C28076Selective Absorption Of Methane By Ionic Liquids (SAMIL)

This third and final stage of this project was the culmination of a ...

C29069Low-Cost Catalyst Materials For Effective VAM Catalytic Oxidation

Application of ventilation air methane (VAM) thermal oxidiser requir...

C23052Novel Stone Dust Looping Process For Ventilation Air Methane Abatement

This multi‐phase project is concerned with the mitigation of m...

Mine Site Greenhouse Gas Mitigation

Low Emission Coal Use

Step-change technologies aimed at reducing greenhouse gas emissions.

Recently Completed Projects

C17060BGasification Of Australian Coals

Four Australian coals were trialled in the Siemens 5 MWth pilot scale ga...

C17060AOxyfuel Technology For Carbon Capture And Storage Critical Clean Coal Technology - Interim Support

The status of oxy-fuel technology for first-generation plant is indicate...

C18007Review Of Underground Coal Gasification

This report consists of a broad review of underground coal gasification,...

Low Emission Coal Use

Mining And The Community

The relationship between mines and the local community.

Recently Completed Projects

C16027Assessing Housing And Labour Market Impacts Of Mining Developments In Bowen Basin Communities

The focus of this ACARP-funded project has been to identify a number...

C22029Understanding And Managing Cumulative Impacts Of Coal Mining And Other Land Uses In Regions With Diversified Economies

The coal industry operates in the context of competing land-uses that sh...

C23016Approval And Planning Assessment Of Black Coal Mines In NSW And Qld: A Review Of Economic Assessment Techniques

This reports on issues surrounding economic assessment and analysis ...

Mining And The Community

NERDDC

National Energy Research,Development & Demonstration Council (NERDDC) reports - pre 1992.

Recently Completed Projects

1609-C1609Self Heating of Spoil Piles from Open Cut Coal Mines

Self Heating of Spoil Piles from Open Cut Coal Mines

1301-C1301Stress Control Methods for Optimised Development...

Stress Control Methods for Optimised Development and Extraction Operations

0033-C1356Commissioned Report: Australian Thermal Coals...

Commissioned Report: Australian Thermal Coals - An Industry Handbook

NERDDC