ACARP ACARP ACARP ACARP
Open Cut

Monitoring of Roof Deformation and Delamination using Deep Hole Multi Point Extensometers

Open Cut » Highwall Mining

Published: June 00Project Number: C9069

Get ReportAuthor: Baotang Shen, Mary Duncan Fama, D Adhikary | CSIRO Exploration & Mining

The work presented in this report is part of the Australian Coal Association Research Program (ACARP) project C9069 "Monitoring of Roof Deformation and Delamination Using Deep-Hole Multi-Point Extensometers". This project is an extension of the ACARP project C8033 "Optimal Design and Monitoring of Layout Stability for Highwall Mining".

Three surface extensometers were installed in Pit 20DU North at the Moura Mine and they recorded the vertical displacements at different depths in the roof strata during the mining of 20 entries and for a period of nearly three months after the completion of mining in this section of the pit.

One extensometer recorded a surprisingly large displacement immediately after mining had passed its location. It is believed that a small scale local roof fall may have triggered this displacement.

Two extensometers recorded increasing roof displacement as mining approached the monitored entry but in a quite opposite manner. One recorded a contraction of the roof strata whereas the other recorded expansion. In both cases, the maximum displacement was about 2mm. It is believed that movement along fault 20DU_R_1 was the major cause of this difference. This fault lay between the two extensometers and was predicted to terminate in the reserve. Movement along this fault could have caused horizontal stresses to increase on one side and to decrease on the other side. The horizontal stress change would have caused the vertical expansion or contraction due to the Poisson effect.

All three extensometers showed some irregularity in displacement variation with depth. The limited accuracy of the extensometers could be the cause of this irregularity. It may also be possible that different horizontal stress change in different roof layers contributed to this irregularity.

Some time dependent vertical displacements were recorded during the three month period after the completion of highwall mining in Pit 20 DU North. The time induced displacements were greater than those recorded immediately following mining. The strong time-dependent effect could be a result of a readjustment of regional horizontal stress in response to exposure to a number of faults in Pit 20DU North. The stress redistribution caused by mining is believed to have been complicated and the readjustment process could take a long period of time to complete.

Apart from the large displacement in Borehole A, no significant displacements in the roof strata were recorded during mining and three months after mining. The extensometer measurements were consistent with field observations and microseismic monitoring results which indicated that the panel in Pit 20DU North was stable during mining and at least for three months after mining.

It needs to be emphasized that the local geology and the rock mass behaviour are often far more complicated than that we have realized. This monitoring exercise was aimed to improve our understanding on the rock mass response to highwall mining. The somehow surprising results appear to have confirmed the complexity of the behaviour of a fractured rock mass. The results are explained based on our best knowledge of the local geology and the rock mass behaviour. However, they could also be caused by other factors which are beyond our understanding and observation.

Underground

Health and safety, productivity and environment initiatives.

Recently Completed Projects

C21013Improving Cavity Prediction On Longwall Faces Through A Combination Of Reliable Convergence, Canopy Attitude And Leg Pressure Monitoring

Most Australian coal mines have shield leg pressure monitoring in real t...

C24014Distributed Acoustic Conveyor Monitoring

CRC Mining have investigated the application of fibre optic Distribu...

C25054Distributed Acoustic Conveyor Monitoring - Phase 2

This project is phase 2 of the distributed acoustic sensing project ...

Underground

Open Cut

Safety, productivity and the right to operate are priorities for open cut mine research.

Recently Completed Projects

C23053A Study Of Sustainability And Profitability Of Grazing On Mine Rehabilitated Land In The Upper Hunter NSW

This study was initiated by the Upper Hunter Mining Dialogue (UHMD) ...

C25035Coal Subsurface Mapping For Open Cut Selective Mining

A reliable coal seam sensing system is required to improve the produ...

C23025Coal Pit Lake Closure By River Flow Through: Risks And Opportunities

In 2011, the river diversion channel around Lake Kepwari, a former o...

Open Cut

Coal Preparation

Maximising throughput and yield while minimising costs and emissions.

Recently Completed Projects

C26007 Revised Dustiness And DEM Test Method (Update Of AS4156.6) Part 2:Preparation

In 2015 project C23054 investigated and reviewed the Australian Stan...

C22033Advanced Control And Optimisation Of DMC Operation

The objective of this project was to develop, implement and demonstr...

C24045Adaptation Of Coal Grain Analysis To Improve Flotation Yield Estimation

Yield estimation from resource data is notoriously difficult. Facto...

Coal Preparation

Technical Market Support

Market acceptance and emphasising the advantages of Australian coals.

Recently Completed Projects

C25045Stage Two - Assessment Of In Situ High-Temperature Strength Of Cokes

Stage I of this project established a reliable and repeatable proces...

C25044Trace Elements In Coal; Status Of Test Methods In Use And Their Applicability

 STAGE 1 REPORT

The key objectives of this stage...

C25042Mechanistic Model Of Coke Development In A Coke Oven Situation

The standard approach to evaluate the potential of coals or blends t...

Technical Market Support

Mine Site Greenhouse Mitigation

Mitigating greenhouse gas emissions from the production of coal.

Recently Completed Projects

C24061Proof-Of-Concept Photocatalytic Destruction Of Methane For Coal Mining Fugitive Emissions Abatement

Australia's fugitive emissions in 2015 were 41 Mt CO2-e (representin...

C23052Novel Stone Dust Looping Process For Ventilation Air Methane Abatement - Phase 3

This multi‐phase project is concerned with the mitigation of m...

C19054VAM Enrichment With A Two-Stage Adsorption Process

Treatment of ventilation air methane (VAM) with cost-effective technolog...

Mine Site Greenhouse Mitigation

Low Emission Coal Use

Step-change technologies aimed at reducing greenhouse gas emissions.

Recently Completed Projects

C17060BGasification Of Australian Coals

Four Australian coals were trialled in the Siemens 5 MWth pilot scale ga...

C17060AOxyfuel Technology For Carbon Capture And Storage Critical Clean Coal Technology - Interim Support

The status of oxy-fuel technology for first-generation plant is indicate...

C18007Review Of Underground Coal Gasification

This report consists of a broad review of underground coal gasification,...

Low Emission Coal Use

Mining And The Community

The relationship between mines and the local community.

Recently Completed Projects

C16027Assessing Housing And Labour Market Impacts Of Mining Developments In Bowen Basin Communities

The focus of this ACARP-funded project has been to identify a number...

C22029Understanding And Managing Cumulative Impacts Of Coal Mining And Other Land Uses In Regions With Diversified Economies

The coal industry operates in the context of competing land-uses that sh...

C23016Approval And Planning Assessment Of Black Coal Mines In NSW And Qld: A Review Of Economic Assessment Techniques

This reports on issues surrounding economic assessment and analysis ...

Mining And The Community

NERDDC

National Energy Research,Development & Demonstration Council (NERDDC) reports - pre 1992.

Recently Completed Projects

1609-C1609Self Heating of Spoil Piles from Open Cut Coal Mines

Self Heating of Spoil Piles from Open Cut Coal Mines

1301-C1301Stress Control Methods for Optimised Development...

Stress Control Methods for Optimised Development and Extraction Operations

0033-C1356Commissioned Report: Australian Thermal Coals...

Commissioned Report: Australian Thermal Coals - An Industry Handbook

NERDDC