ACARP ACARP ACARP ACARP
Underground

Cable-Safe System for Shuttle Cars

Underground » Roadway Development

Published: August 00Project Number: C9004

Get ReportAuthor: Bob Ifield | Hyden Engineering

The objective of the project was to improve safety and to reduce the costs associated with failures of trailing cables, through the application of a new product that may be retrofitted to existing fleets. This product: (1) increases the minimum tension to reduce failures resulting from the formation of 'loops' in the cable and failures from the car crushing its own cable, and (2) decreases the maximum tension to reduce failures from tension overload.

Cable tension decreases as the cable reel fills and is therefore at a minimum at the anchor. It also decreases as the vehicle accelerates towards the anchor and, with several build standards, this is compounded at the boot end by the actuation of the conveyor cylinder. Thus cable failures due to 'loops', and from the car crushing its own cable, will predominantly occur near the anchor and probably during the pay-out process that immediately follows reeling-in under low tension.

Low tension may also occur due to losses at the Archimedes and guide rollers, since these losses subtract from the torque available to the reel. These losses are particularly high when the car is cornering, as demonstrated during earlier underground tests at Myuna.

Highest tension occurs during pay-out with a near empty reel and since this is where the bend radius is minimum, the condition for the cable is severe. Resulting elongation travels along the cable to the loose end causing 'knuckling' at the anchor.

The design achieved the constant tension objective and should provide relief to the cable problem. One component of the design is already proven through underground use at Appin, Myuna and Southland mines.

The CT (constant tension) design provides 90-kg tension for both the reel-in and pay-out modes. It reduces tension during pay-out, with a near empty reel, by a factor of 2 and increases tension during reel-in, with a full reel, by a factor of 1.8. 4

Tests at Appin mine, midway through the project, indicated that extreme transient loads occurred when 'bumps' in the road are encountered and that these were higher than targeted by the project and by the devices developed. While tensions in excess of 400 kg frequently occurred, some tests produced loads in excess of 1000 kg. The recommended maximum tension is 150 kg for 25mm cables and 210 kg for 35mm cables.

Industry representatives, invited to review the project, recommended an expansion to the 'bump' studies and this decision postponed the completion of development and underground testing of the CT system. These representatives also concluded that the 'Appin' test track may not be representative and proposed a different 'bump' test (refer appendix).

The new test track produced less violent 'pitching' of the vehicle and generally the shock loads to the cable were less than 400kg. A key finding, from the additional 'bump' tests, was that the shocks to the cable were not directly related to the proximity of the bump to the anchor but were related to the amount of cable on the reel at the time.

A new anchor device improved the protection against shock for bumps in close proximity, but this had a reducing benefit as the distance between the bump and anchor increased. The decision to vary the project was validated since the additional study determined other causes of failure, providing direction for further study and a need to consider interim operational restrictions. Given the assessment that the 'Appin' tests were extreme, this study has provided solutions to the majority of problems concerning cables and has identified means of dealing with the remainder. However, some engineers have questioned the assessment made regarding 'bumps' and further input is now sought.

Underground

Health and safety, productivity and environment initiatives.

Recently Completed Projects

C33029Review Longwall Face Ventilation To Mitigate Goaf Gas Emissions Onto Walkways And Tailgate End

As longwall mining increasingly targets deeper coal seams, managing ...

C29009Control Of Transient Touch Voltages During Switching

There have been an increasing number of electric shock incidents rep...

C29025Effectiveness Of Shotcrete In Underground Coal Mines

The primary objective of this project is to quantify the effectivene...

Underground

Open Cut

Safety, productivity and the right to operate are priorities for open cut mine research.

Recently Completed Projects

C33036Radar Tyre Monitor System

This project focussed on trialling a radar sensing technology design...

C26020Preventing Fatigue Cracking Via Proactive Surface Dressing

Fatigue cracking of plant and equipment presents a significant chall...

C33046Rationale For The Use Of Paired Continuous Real Time Noise Monitors To Reduce Uncertainty In The Quantification Of Noise From Open Cut Coal Mines

Numerous experimental studies of varying duration have been undertak...

Open Cut

Coal Preparation

Maximising throughput and yield while minimising costs and emissions.

Recently Completed Projects

C34041A Coal Spiral For The 2020S

The objective of this project is to develop an enhanced coal process...

C33057Foreign Contaminants Detection On Conveyor Belts Using Digital Imaging Processing Techniques And Coal Penetrating Sensors

This project was initiated to tackle the ongoing issue of foreign co...

C29065Wash Plant Fines Testing Methods Enhancement

Accurately estimating the proportion of expected fine size material ...

Coal Preparation

Technical Market Support

Market acceptance and emphasising the advantages of Australian coals.

Recently Completed Projects

C34054Scoping Study: Design Of Cokes From Biomass-Coal Blends For Sustainable Blast Furnace Ironmaking

There is an increasing focus on improving the environmental sustaina...

C34058Strength Development In Fouling Deposits

When coal is combusted in a boiler, the fly ash that is produced flo...

C34059Coke Reactivity With CO2 And H2O And Impacts On Coke Microstructure And Gas Diffusion

With the global shift to low-carbon ironmaking, partial substitution...

Technical Market Support

Mine Site Greenhouse Gas Mitigation

Mitigating greenhouse gas emissions from the production of coal.

Recently Completed Projects

C34066Safe Operation Of Catalytic Reactors For The Oxidation Of VAM Operating Under Abnormal Reaction Conditions

The catalyst Pd/TS-1 has shown excellent activity in oxidising venti...

C28076Selective Absorption Of Methane By Ionic Liquids (SAMIL)

This third and final stage of this project was the culmination of a ...

C29069Low-Cost Catalyst Materials For Effective VAM Catalytic Oxidation

Application of ventilation air methane (VAM) thermal oxidiser requir...

Mine Site Greenhouse Gas Mitigation

Low Emission Coal Use

Step-change technologies aimed at reducing greenhouse gas emissions.

Recently Completed Projects

C17060BGasification Of Australian Coals

Four Australian coals were trialled in the Siemens 5 MWth pilot scale ga...

C17060AOxyfuel Technology For Carbon Capture And Storage Critical Clean Coal Technology - Interim Support

The status of oxy-fuel technology for first-generation plant is indicate...

C18007Review Of Underground Coal Gasification

This report consists of a broad review of underground coal gasification,...

Low Emission Coal Use

Mining And The Community

The relationship between mines and the local community.

Recently Completed Projects

C16027Assessing Housing And Labour Market Impacts Of Mining Developments In Bowen Basin Communities

The focus of this ACARP-funded project has been to identify a number...

C22029Understanding And Managing Cumulative Impacts Of Coal Mining And Other Land Uses In Regions With Diversified Economies

The coal industry operates in the context of competing land-uses that sh...

C23016Approval And Planning Assessment Of Black Coal Mines In NSW And Qld: A Review Of Economic Assessment Techniques

This reports on issues surrounding economic assessment and analysis ...

Mining And The Community

NERDDC

National Energy Research,Development & Demonstration Council (NERDDC) reports - pre 1992.

Recently Completed Projects

1609-C1609Self Heating of Spoil Piles from Open Cut Coal Mines

Self Heating of Spoil Piles from Open Cut Coal Mines

1301-C1301Stress Control Methods for Optimised Development...

Stress Control Methods for Optimised Development and Extraction Operations

0033-C1356Commissioned Report: Australian Thermal Coals...

Commissioned Report: Australian Thermal Coals - An Industry Handbook

NERDDC