ACARP ACARP ACARP ACARP
Open Cut

Highwall Mining Backfill

Open Cut » Highwall Mining

Published: October 99Project Number: C6014

Get ReportAuthor: Ian Clark, Graeme Boyd | The Minserve Group

This report studies the potential of using backfill to increase the coal recovery. It is developed from the premis that placed fill will provide pillars with additional confirming pressure thereby increasing both their load leaving capacity and stability.

Backfilling CHM entries using colliery rejects is demonstrated in this study as being both technically and economically viable. However the target benefit of backfilling, defined as allowing 70% plan area recovery of 4m to 8m thick coal seams cannot be met for 4m single pass CHM mining. This is due to adverse mechanisms of slender pillar deformation being determined for pillars with a slenderness ratio (w/h) of less than 0.50. This constraint would limit recoveries (plan area) to 64%. In many seams where the seam strength (UCS basis) is less than 7MPa to 8MPa, this level of recovery exceeds the 52% to 58% recovery that might be achieved without backfill.

For two-pass highwall mining of seams greater than 4m in thickness, it was found that by using a 3% cement stabilised paste backfilled that cures to 1MPa crushing strength, significant plan area recoveries of up to 64% are possible by staged backfilling of the lower pass. The backfilled stabilised lower pass pillars isolate support requirements to the upper pass pillars, hence 8m thick seams can be mined with 2m thick pillars.

Without backfill, a 8m thick seam could only be highwall mined for a 30% plan area recovery.

The findings from this research study are considered to demonstrate, with some certainty, that field trials to confirm backfilling specification and pillar support performance is warranted. Given the ubiquitous properties of washery rejects, most sites would qualify for field trials. A major opportunity to realise the benefits of backfilling is suggested for Wambo Colliery, where high slimes contents tailings have proved problematical and costly to dispose. Such materials could form high density fluidised slurries or high solids content pastes for use as backfill material, capable of generating good pillar confinement.

Sufficient "seed" information on reject preparation and slurry transport and discharge into CHM entries is presented to work up a more detailed proposal for field trials.

Underground

Health and safety, productivity and environment initiatives.

Recently Completed Projects

C34019Longwall Bretby Cable Handling Monitoring With Fibre Optics

This project examined the potential of using fibre optic sensing tec...

C28028The Inclusion Of High Interest Native Plants In Mine Site Restoration Programs: Propagation, Translocation And Field Re-Introduction

This report synthesises over 10 years of ex situ and in si...

C27049Mine Machine Radar Sensor Integration

The aim of this project was to develop an integrated radar sensor an...

Underground

Open Cut

Safety, productivity and the right to operate are priorities for open cut mine research.

Recently Completed Projects

C34029Validation Of Laser Induced Breakdown Spectroscopy (LIBS) As A Rapidly Deployable Field Technology To Estimate Coal Quality

Rapid evaluation of a coal resource by in-situ characterisation dow...

C34028Guidelines For Assessment Of Geotechnically Safe And Stable Post-Mining Landforms

The purpose of this project was to develop a guidelines document as ...

C34016Elements In Coal – A Start-To-End Analysis

This project explores the fate and concentration potential of critical e...

Open Cut

Coal Preparation

Maximising throughput and yield while minimising costs and emissions.

Recently Completed Projects

C26016Determining The Benefits Of Online Thickener Underflow Rheology Measurements

The aim of this project is to determine how useful the rheology meas...

C33056Modelling And Control Of Classifying Cyclones

Hydrocyclones are one of the key technologies for the classification...

C28056Surface Alloying Of Centrifuge Baskets And Sieve Bends Screen Surfaces To Increase The Service Lifetime

The main objective of this project was to improve the wear resistanc...

Coal Preparation

Technical Market Support

Market acceptance and emphasising the advantages of Australian coals.

Recently Completed Projects

C33066Washability And Distribution Of Sulfur And Trace Elements For Different Size And Density Fractions Of Raw Coals

Based on the hypothesis that the levels of sulfur and other toxic tr...

C34060In-Situ Investigation Of Coke Structure Formation Under Stamp Charged Coking Conditions

Stamp charged cokemaking has emerged as an effective technique to im...

C34062Improving The Classification Of Microstructure Distribution In Coke CT Images Using Deep Learning And Lineal Path Calculations

This project builds on a number of earlier projects that have helped...

Technical Market Support

Mine Site Greenhouse Gas Mitigation

Mitigating greenhouse gas emissions from the production of coal.

Recently Completed Projects

C28076Selective Absorption Of Methane By Ionic Liquids (SAMIL)

This third and final stage of this project was the culmination of a ...

C29069Low-Cost Catalyst Materials For Effective VAM Catalytic Oxidation

Application of ventilation air methane (VAM) thermal oxidiser requir...

C23052Novel Stone Dust Looping Process For Ventilation Air Methane Abatement

This multi‐phase project is concerned with the mitigation of m...

Mine Site Greenhouse Gas Mitigation

Low Emission Coal Use

Step-change technologies aimed at reducing greenhouse gas emissions.

Recently Completed Projects

C17060BGasification Of Australian Coals

Four Australian coals were trialled in the Siemens 5 MWth pilot scale ga...

C17060AOxyfuel Technology For Carbon Capture And Storage Critical Clean Coal Technology - Interim Support

The status of oxy-fuel technology for first-generation plant is indicate...

C18007Review Of Underground Coal Gasification

This report consists of a broad review of underground coal gasification,...

Low Emission Coal Use

Mining And The Community

The relationship between mines and the local community.

Recently Completed Projects

C16027Assessing Housing And Labour Market Impacts Of Mining Developments In Bowen Basin Communities

The focus of this ACARP-funded project has been to identify a number...

C22029Understanding And Managing Cumulative Impacts Of Coal Mining And Other Land Uses In Regions With Diversified Economies

The coal industry operates in the context of competing land-uses that sh...

C23016Approval And Planning Assessment Of Black Coal Mines In NSW And Qld: A Review Of Economic Assessment Techniques

This reports on issues surrounding economic assessment and analysis ...

Mining And The Community

NERDDC

National Energy Research,Development & Demonstration Council (NERDDC) reports - pre 1992.

Recently Completed Projects

1609-C1609Self Heating of Spoil Piles from Open Cut Coal Mines

Self Heating of Spoil Piles from Open Cut Coal Mines

1301-C1301Stress Control Methods for Optimised Development...

Stress Control Methods for Optimised Development and Extraction Operations

0033-C1356Commissioned Report: Australian Thermal Coals...

Commissioned Report: Australian Thermal Coals - An Industry Handbook

NERDDC