ACARP ACARP ACARP ACARP
Underground

Longwall Gateroad Development Systems, Belt Top Pantechnicon

Underground » Roadway Development

Published: January 99Project Number: C4015B

Get ReportAuthor: K Hall, Keith Robinson | Illawarra Conveyor Services

This Brief summarises the development of the Fan Trolley and Material Trolley. The project was sponsored by Springvale Colliery, in association with Illawarra Conveyor Services, Wollongong

Springvale Colliery had a requirement to provide auxiliary ventilation across the longwall face in order to mine past a fall in the tailgate zone. As a belt conveyor structure was already installed, it was proposed to mount a fan on the conveyor structure and move the fan outbye with the face retreat, keeping the auxiliary fan the required distance along the gateroad.

The aim of this project was to develop a set of equipment capable of supporting "Pantechnicon" type equipment and a set of equipment capable of transporting materials along the belt structure. These materials would support the longwall retreat system or roadway development.

The project essentially consisted of five stages.

Investigate the Load Carrying Potential of the Belt Conveyor Structure

The objective was to confirm by calculation and physical testing the practical loading that could be applied to the existing structure. Two bays of the 1200mm belt conveyor structure in use at Springvale Colliery were assembled and tested with 1200kg suspended along the troughing idlers to simulate coal and belt mass. An additional 3800kg was added to the idler centres of the stringers across the two bays. Measured deflection of the stringers fell within Australian Standards acceptances.

Design and Manufacture of a Fan Trolley

The design of the fan trolley needed to be such that components could be used and adapted to other applications. For this project, Springvale required an 18m3 Howden ventilation fan to be transported along the maingate, on the conveyor structure. The trolley was designed to use eight wheels mounted on four bogie arms. The bogie arms were centre pivoted and attached to two axles. The axles were then attached to a chassis that was purpose built for the fan. The trolley also employed a three point suspension system.

Mounting the Fan on the Belt Structure

The components of the fan trolley were manufactured, assembled and then attached to the chassis. A separate trolley had to be designed and built for the fan's starter box to also be mounted on the belt structure. The starter and fan trolleys were linked by two stiff arm linkages, long enough to provide room for the ventilation duct to be attached to the fan.

The fan trolley was taken underground and assembled on the structure outbye of the longwall maingate. The fan was stabilised using legs set between the floor and the roof. As the longwall was retreated to a planned position, the fan was operated to provide exhaust ventilation through special ducting across the longwall face. As the longwall was retreated to a planned position, the fan was moved 100m outbye along the belt structure using a winch system. Once the move was complete, the fan was again established and used to ventilate the longwall face.

Development of an Air Hydraulic Drive System to Allow the Trolley System to be Self Propelled

After the successful operation of the trolley system, it was decided to examine incorporating a drive system to make the fan trolley (and any other trolley developed in the future) self propelling.

The designed drive system incorporated an air/hydraulic power unit that would provide hydraulic power to a set of motors attached to the wheels of the trolley. The system also included a failsafe braking system.

Thirty metres of 1500mm belt structure was setup for the testing of the fan trolley drive system. The design called for the fan to be able to negotiate a 1:10 incline as well as a maximum structure elevation misalignment of 100mm across the structure and up to 420mm over two bays longitudinally. The results of the tests are listed overleaf.

Maximum Tramming speed Level -20m/min

1:10 Incline - 10m/min

1:10 Decline - 22m/min

Stopping distance (from 22m/min) 100mm in 7sec (deceleration = 0.524m/s2)
Driving on wet stringers - Negotiating a 1:10 incline with stringers wet with water, coal dust, mud. Trolley climbed incline satisfactorily.

Trolley trammed down gradient and stopped satisfactorily

Creep Test - Trolley left parked on a incline for 1 hour. The trolley did not move over the course of this 1 hour.
Braking Force of the system (max). 12kN
Braking Force required (max). 2.352kN
Driving Force of the system (max) 11kN
Driving Force required (max) 4.7kN

 

Entrapment/Captivation

In order to guard against dramatic changes of alignment along the structure, and any situation where articulation was exceeded beyond permissible ranges, a system was needed to captivate the trolleys on the structure.

The captivation system does not lock the trolley to the structure, rather it stops the trolley wheels being able to leave the stringer. This was achieved by bolting purpose designed brackets to the bogie arms that would come into contact with the outer side of the stringer thus limiting the movement of the trolley on the structure. If a wheel did come off the stringer, the bracket would act as a catcher.

With the system proven to its current stage, it was then decided to design and build a trolley capable of carrying a wide range of materials and equipment.

The final design used the same axles, bogie arms, wheel hubs, wheels and drive bosses as the fan trolley. By using this equipment the same brake/motor drive units could be used thus making the parts interchangeable. This also meant that the mine would not have to carry a wide range of spare parts for the trolley. The final flat deck design was made 1800mm wide x 3500mm long and had a minimum deck height of 1350mm from the floor.

Outcomes

The main outcome of this project has been the utilisation of the previously wasted space above the conveyor belt. The project has proved that the trolley system combined with the structure can be used to move substantial equipment and supplies along a gateroad or development panel belt.

In trials at Springvale Colliery, the following benefits were seen:

  • Improved overall belt installation standards
  • Less people required to move materials (the fan) and reduced likelihood of damage to materials (the fan)
  • Minimisation of disruption to maintenance activities and service moves
  • Moving of fan is independent of the boot end location

Other foreseeable benefits include providing a known location for tools, equipment materials and spare parts. With these items mounted on the structure they would be less vulnerable to damage.

There is significantly potential for this equipment to improve mining systems. Use of this system may improve productivity by decreasing the amount of time spent moving services and equipment, thus increasing time spent cutting coal.

The final report includes considerable detail on the trials undertaken and the resultant trolley design.

 

Underground

Health and safety, productivity and environment initiatives.

Recently Completed Projects

C34019Longwall Bretby Cable Handling Monitoring With Fibre Optics

This project examined the potential of using fibre optic sensing tec...

C27049Mine Machine Radar Sensor Integration

The aim of this project was to develop an integrated radar sensor an...

C29007Innovative Coal Burst System To Investigate The Influence Of Confinement Loss And Pre-Conditioning On Coal Burst Mechanism

The challenges associated with designing and operating a safe and pr...

Underground

Open Cut

Safety, productivity and the right to operate are priorities for open cut mine research.

Recently Completed Projects

C33035High Water Recovery, Low Cost Desalination Using PV-Powered Membrane Capacitive Deionisation (Mcdi)

Capacitive deionization is a robust, energy efficient and cost effec...

C28035Topsoil Deficits In Site Rehabilitation Accelerated Transformation Of Spoils To Functional Soils

The incorporation of commercial biological amendments (compost, worm...

C34036Tyre Handler Testing Rig Stage 2: Lifting Trials

Tyre handling is a major source of risk in surface mining operations...

Open Cut

Coal Preparation

Maximising throughput and yield while minimising costs and emissions.

Coal Preparation

Technical Market Support

Market acceptance and emphasising the advantages of Australian coals.

Technical Market Support

Mine Site Greenhouse Gas Mitigation

Mitigating greenhouse gas emissions from the production of coal.

Recently Completed Projects

C28076Selective Absorption Of Methane By Ionic Liquids (SAMIL)

This third and final stage of this project was the culmination of a ...

C29069Low-Cost Catalyst Materials For Effective VAM Catalytic Oxidation

Application of ventilation air methane (VAM) thermal oxidiser requir...

C23052Novel Stone Dust Looping Process For Ventilation Air Methane Abatement

This multi‐phase project is concerned with the mitigation of m...

Mine Site Greenhouse Gas Mitigation

Low Emission Coal Use

Step-change technologies aimed at reducing greenhouse gas emissions.

Recently Completed Projects

C17060BGasification Of Australian Coals

Four Australian coals were trialled in the Siemens 5 MWth pilot scale ga...

C17060AOxyfuel Technology For Carbon Capture And Storage Critical Clean Coal Technology - Interim Support

The status of oxy-fuel technology for first-generation plant is indicate...

C18007Review Of Underground Coal Gasification

This report consists of a broad review of underground coal gasification,...

Low Emission Coal Use

Mining And The Community

The relationship between mines and the local community.

Recently Completed Projects

C16027Assessing Housing And Labour Market Impacts Of Mining Developments In Bowen Basin Communities

The focus of this ACARP-funded project has been to identify a number...

C22029Understanding And Managing Cumulative Impacts Of Coal Mining And Other Land Uses In Regions With Diversified Economies

The coal industry operates in the context of competing land-uses that sh...

C23016Approval And Planning Assessment Of Black Coal Mines In NSW And Qld: A Review Of Economic Assessment Techniques

This reports on issues surrounding economic assessment and analysis ...

Mining And The Community

NERDDC

National Energy Research,Development & Demonstration Council (NERDDC) reports - pre 1992.

Recently Completed Projects

1609-C1609Self Heating of Spoil Piles from Open Cut Coal Mines

Self Heating of Spoil Piles from Open Cut Coal Mines

1301-C1301Stress Control Methods for Optimised Development...

Stress Control Methods for Optimised Development and Extraction Operations

0033-C1356Commissioned Report: Australian Thermal Coals...

Commissioned Report: Australian Thermal Coals - An Industry Handbook

NERDDC