ACARP ACARP ACARP ACARP
Open Cut

Improved Dragline Productivity Through Rigging Design

Open Cut » Overburden Removal

Published: July 97Project Number: C4003

Get ReportAuthor: Terry O'Beirne, Graham Lumley | ACIRL

ACIRL Ltd was commissioned by ACARP to investigate and research aspects of dragline bucket rigging, (Project C4003). This project commenced in May 1995 and was completed in October 1996. The total project value was $195,000 of which ACARP provided funding for $150,000. The following organisations contributed a total of $45,000 to the project:

  • Collinsvale Coal Company Pty Ltd
  • Tarong Coal
  • Ulan Coal Mines Ltd
  • Drayton Coal Pty Ltd
  • Warkworth Mining Ltd
  • Mt Thorley Operations
  • Barlows equipment Manufacturing Co Ltd

The project was broken into three stages:

Stage 1 was an audit of Australian dragline rigging usage;

Stage 2 was to quantify effects on bucket performance of basic changes to specific aspects of conventional rigging;

Stage 3 was to investigate modifications to existing rigging and new rigging arrangements.

There are no simple global answers to optimising the performance of a dragline bucket. Many factors, (often site-specific), can affect different aspects of behaviour to varying degrees. For example, there are completely independent factors that affect digging, disengaging, carrying, dumping and chopping. These factors may also be in conflict with each other e.g. maintain satisfactory carry angle, minimise dump rope load.

It is important to understand the inherently complex and dynamic nature of dragline bucket and rigging performance. A small change in one aspect, eg. dump rope length, may radically affect aspects of behaviour in ways that were completely unexpected. In addition a change in one variable often requires change in another to compensate and/or enhance the ultimate performance.

With this in mind, two approaches were taken to achieve the aims of this project:

A specific approach, whereby the individual parts of the system were examined and their effects analysed.

A global viewpoint, which considered the entire system as a whole.

It should be noted that where conventional rigging is referred to, the BE HPS system of connecting hoist chains on the inside of the bucket without a spreader bar is precluded.

Objectives

This project had the following as its key objectives:

  • provide a better understanding of what others are doing with dragline rigging;
  • provide a better understanding of the potential productivity gains/losses which may be achieved/incurred through correct/incorrect rigging and the best methods of achieving gains;
  • identify and evaluate novel changes to the conventional rigging arrangements.

Conclusions and Recommendations

The typical drag assembly is either 25 drag links plus two pear links or 24 drag links plus two pear links plus a hitch link. In each case a total of 27 links. There are some operations which use as low as 21 links. The typical lower hoist assembly is 9 or 11 links plus 2 stud or pear links. Unlike the drag assembly there is not a large capacity to vary the length of the hoist chain; shortening the hoist chain causes the lug on the arch to run into the block while lengthening them reduces the dumping height and could increase rehandle. The typical upper hoist chain is very similar to the lower hoist chain having 9 or 11 links plus 2 stud or pear links.

Many mines use old hoist rope for the dump rope. There does not appear to be any negative impact on rope life by doing this relative to using new rope. Generally the BE1370W and M8050 class machines are using 83mm rope.

The smaller class machines are using 64mm or 76mm while the BE1570W / M8200 class machines are using 92mm rope. The majority of the BE1370W and M8050 class machines are using 1040mm diameter dump block sheaves although some use 1220mm sheaves. The standard case of 83mm rope going over a 1040mm sheave gives a D/d ratio of 12.5. The discussions with minesite personnel indicated a strong belief that the thicker rope provided more strength and improved life.

In AS1418.1, the action of the dump rope corresponds to a mechanism classification of M1. Dump ropes could be assumed to be classified as under an L4 (Very Heavy - Mechanisms subjected regularly to the maximum load) category. These two together indicate that there is no appropriate class of utilisation for the item (with D-d ratio of 12.5) and a total duration of use of less than 200 operating hours is predicted. Assuming the dragline actually cycles (not including non-operating time and walking) for 70% of the time the dump rope life will be less than 11.9 days.

Over time each mine should successively try 76mm, 70mm and 64mm as each of these has sufficient strength to withstand the peak loads and the increased D-d ratio should provide improved life. Alternatively this report has recommended further industry funded work on improving dump rope life and these trials could be included in this work.

There is no production related reason for using double dump ropes rather than a single dump rope. Where feasible a single dump rope should always be used.

The rigging components which have the lowest reliability (determined qualitatively from minesite visits) are:

  • Dump Ropes
  • Drag Shackles
  • Lower Hoist Chain - third link
  • Locking Pins

There is no discernible trend in optimum carry angle between conventional buckets (hoist chains on outside of bucket with spreader bar) with respect to spoil and bucket geometry. The BH 3 records a significantly lower optimum carry angle than the conventional buckets. The average value is 35.5° with standard deviation 1.1°. It is suggested that the carry angle of the bucket be set slightly below the average as there is a tendency for the carry angle of the bucket to increase as components wear. The conclusion is to set the rigging (chain and dump rope lengths) so that the angle of the bottom of the bucket is approximately 35° to the horizontal at the point where the drag hitch is 27.5 metres away from the fairleads and 10 metres below them. Due to operational factors this angle will change over time. Once it falls below 33.5°(-2) or exceeds 37.5° (+2) the dump rope length should be varied to bring the angle back to 35°. Under normal statistical process control techniques, the limits are set at plus and minus three standard deviations. However, in this work, two standard deviations are suggested, as the value of production is very high.

Neither the average payload for a specific bucket nor dump rope loads are impacted positively or negatively by varying chain lengths (provided interactions in the rigging are avoided) so long as the bucket is set to the optimum carry angle at the specified point (bucket equilibrium

The 'rigging modification rules' are similar fro all conventional buckets (all except the BE HPS bucket). There do not appear to be any trends with respect to bucket geometry. The average values are:

  • Optimum Bucket Carry Angle 35.5°;
  • Reduce dump rope length by 0.25m for every one degree increase in carry angle required;
  • Increase dump rope length by 0.70 metre for every 2 additional links added to drag chains (converse is also true);
  • Increase dump rope length by 1.15 metres for every 2 additional links added to lower hoist chains (converse is also true);
  • Increase dump rope length by 1.80 metres for every 2 additional links added to upper hoist chains (converse is also true).

 

Underground

Health and safety, productivity and environment initiatives.

Recently Completed Projects

C33029Review Longwall Face Ventilation To Mitigate Goaf Gas Emissions Onto Walkways And Tailgate End

As longwall mining increasingly targets deeper coal seams, managing ...

C29009Control Of Transient Touch Voltages During Switching

There have been an increasing number of electric shock incidents rep...

C29025Effectiveness Of Shotcrete In Underground Coal Mines

The primary objective of this project is to quantify the effectivene...

Underground

Open Cut

Safety, productivity and the right to operate are priorities for open cut mine research.

Open Cut

Coal Preparation

Maximising throughput and yield while minimising costs and emissions.

Recently Completed Projects

C33057Foreign Contaminants Detection On Conveyor Belts Using Digital Imaging Processing Techniques And Coal Penetrating Sensors

This project was initiated to tackle the ongoing issue of foreign co...

C29061Improving Flotation With A Combined Method

This project aimed to develop and assess a method combining the use ...

C33053Improving Centrifugal Dewatering Via Modelling And Analysis

The aim of the project was to develop a model for screen bowl centri...

Coal Preparation

Technical Market Support

Market acceptance and emphasising the advantages of Australian coals.

Recently Completed Projects

C34059Coke Reactivity With CO2 And H2O And Impacts On Coke Microstructure And Gas Diffusion

With the global shift to low-carbon ironmaking, partial substitution...

C34055Factors Underpinning The Gasification Reactivity Of Coke RMDC And IMDC With CO2

It is well known that the gasification reactivity of metallurgical c...

C33066Washability And Distribution Of Sulfur And Trace Elements For Different Size And Density Fractions Of Raw Coals

Based on the hypothesis that the levels of sulfur and other toxic tr...

Technical Market Support

Mine Site Greenhouse Gas Mitigation

Mitigating greenhouse gas emissions from the production of coal.

Recently Completed Projects

C34066Safe Operation Of Catalytic Reactors For The Oxidation Of VAM Operating Under Abnormal Reaction Conditions

The catalyst Pd/TS-1 has shown excellent activity in oxidising venti...

C28076Selective Absorption Of Methane By Ionic Liquids (SAMIL)

This third and final stage of this project was the culmination of a ...

C29069Low-Cost Catalyst Materials For Effective VAM Catalytic Oxidation

Application of ventilation air methane (VAM) thermal oxidiser requir...

Mine Site Greenhouse Gas Mitigation

Low Emission Coal Use

Step-change technologies aimed at reducing greenhouse gas emissions.

Recently Completed Projects

C17060BGasification Of Australian Coals

Four Australian coals were trialled in the Siemens 5 MWth pilot scale ga...

C17060AOxyfuel Technology For Carbon Capture And Storage Critical Clean Coal Technology - Interim Support

The status of oxy-fuel technology for first-generation plant is indicate...

C18007Review Of Underground Coal Gasification

This report consists of a broad review of underground coal gasification,...

Low Emission Coal Use

Mining And The Community

The relationship between mines and the local community.

Recently Completed Projects

C16027Assessing Housing And Labour Market Impacts Of Mining Developments In Bowen Basin Communities

The focus of this ACARP-funded project has been to identify a number...

C22029Understanding And Managing Cumulative Impacts Of Coal Mining And Other Land Uses In Regions With Diversified Economies

The coal industry operates in the context of competing land-uses that sh...

C23016Approval And Planning Assessment Of Black Coal Mines In NSW And Qld: A Review Of Economic Assessment Techniques

This reports on issues surrounding economic assessment and analysis ...

Mining And The Community

NERDDC

National Energy Research,Development & Demonstration Council (NERDDC) reports - pre 1992.

Recently Completed Projects

1609-C1609Self Heating of Spoil Piles from Open Cut Coal Mines

Self Heating of Spoil Piles from Open Cut Coal Mines

1301-C1301Stress Control Methods for Optimised Development...

Stress Control Methods for Optimised Development and Extraction Operations

0033-C1356Commissioned Report: Australian Thermal Coals...

Commissioned Report: Australian Thermal Coals - An Industry Handbook

NERDDC