ACARP ACARP ACARP ACARP
Open Cut

Dynacut Fundamental Development and Scalability Testing

Open Cut » Overburden Removal

Published: April 21Project Number: C26035

Get ReportAuthor: Isaac Dzakpata, Dihon Tadic, Joji Quidim, Amin Mousavi, Kristyn Zoschke and Kasun Kalhara | Mining3

The previous project outcomes (C25041) supported the potential for DynaCut technology to be effective and economically competitive at a large scale for surface coal mining. This phase aimed to progress the de-risking process through additional cutting trials with a modified cutting system, as well as advance mining system concepts and establish key design criteria for the next-generation DynaCut test machine.

Cutting tests were performed using the DynaCut test machine and sandstone sample blocks cemented into a cutting bunker. The rocks spanned two domains: ~20 MPa UCS and ~30 MPa UCS. The machine was modified to allow variation of the oscillating dynamics of the cutting disc, to test the hypothesis that reconfiguring the way that the cutting energy is applied to the rock may improve the efficiency of cutting, and therefore the overall performance of the system, in overburden materials. The testing comprised over 200 individual cuts, providing 29 test cuts in the sandstone blocks.

Key performance metrics for the cutting tests were the ICR (instantaneous cutting rate) and SE (specific energy of cutting). Whilst increasing the total cutting power (via increased oscillation frequency and/or increased energy per cutter cycle with a higher oscillating mass) delivered improved cutting rates, the key finding was that the cutting efficiency could indeed be significantly improved by simply reconfiguring the way that total power was delivered. In fact, the most efficient cutting was achieved by increasing the oscillating mass whilst simultaneously reducing the oscillation frequency, delivering a reduction in SE of about 25%, without any detrimental effect on the cutting rate.

Cutter designs for overburden materials were also advanced during this project. Whilst a sharper or more aggressive cutter is generally required for weaker/softer materials, there is a balance between this sharpness and the strength of the cutter body, and therefore different designs may still be required for different domains of overburden materials. Features of the cutting face and rock mass, such as free surfaces and mechanical discontinuities, also offer potential for further enhancement of overall excavation performance through considered cut sequencing and path planning.

A process of engineering review, combined with further conceptualisation of potential surface mining systems, provided clarification of the key requirements and design features for an up-scaled test machine. It was determined that the upper limit of a single cutter unit, without major re-engineering of the core components, is likely to be a cutter of about 1m diameter with a cartridge about three times more powerful than the current system.

High-potential commercial systems include a surface longwall style system and mobile machine style system. An upscaled surface longwall style system with two shearers could potentially cut at a rate of about 2300 bcm/h (ICR). For the mobile machine style of cutting system, an up-scaled single-cutter machine could potentially cut at a rate of about 540 bcm/h (ICR), whilst a much larger multi-cutter machine might be capable of >2000 bcm/h.

Previous economic evaluations for future high-capacity commercial production systems were revised, indicating a total all-in cost of $3.01/bcm for a mobile machine-based system, and $2.95/bcm for a surface longwall style system. These revised cost estimates further strengthen the potential competitiveness of DynaCut, with the all-in cost for conventional mining in the same scenario being about $3.00/bcm.

A more comprehensive performance and cost assessment was also performed, with a case study deposit scenario and various scales of lower-capacity single-cutter machines with multiple material transport systems. Whilst the OpEx and CapEx of the DynaCut systems are typically higher than that of conventional mining, there are systems that are likely very competitive on an OpEx basis e.g. DynaCut-conveyor system: $4.40-$5.50/bcm; baseline system: $4.60-$5.00/bcm. CapEx estimates for the complete DynaCut system fleets ($46M to $68M) were also higher than for the baseline system ($34M). Various benefits offered by continuous cutting (e.g. potential for steeper pit slopes, increased coal recovery, elimination of blasting-related impacts) must be considered alongside the simple metrics of OpEx and CapEx. Applying basic examples of these to the case study mining scenario actually resulted in the DynaCut-conveyor system outperforming the baseline drill/blast/load operation, despite having higher OpEx and CapEx per bcm.

The ultimate scale of the individual cutting units of a DynaCut system may not be as large as originally envisaged, and it may be feasible to base an MVP (minimum viable prototype) for initial deployment on an existing platform. The MVP ideally requires a larger cutter (towards 1m diameter), and needs improved mobility and stability, whilst allowing more continuous operation and appropriate cuttings management.

The outcomes of this phase are extremely encouraging, highlighting that there is likely much additional potential to be discovered as the DynaCut technology is further tested, developed and refined. An extended site deployment opportunity with a suitable prototype machine is a pivotal requirement for de-risking the continued development of the technology for application in surface coal mining, and accelerating adoption into suitable operations.

Underground

Health and safety, productivity and environment initiatives.

Recently Completed Projects

C34019Longwall Bretby Cable Handling Monitoring With Fibre Optics

This project examined the potential of using fibre optic sensing tec...

C28028The Inclusion Of High Interest Native Plants In Mine Site Restoration Programs: Propagation, Translocation And Field Re-Introduction

This report synthesises over 10 years of ex situ and in si...

C27049Mine Machine Radar Sensor Integration

The aim of this project was to develop an integrated radar sensor an...

Underground

Open Cut

Safety, productivity and the right to operate are priorities for open cut mine research.

Recently Completed Projects

C34029Validation Of Laser Induced Breakdown Spectroscopy (LIBS) As A Rapidly Deployable Field Technology To Estimate Coal Quality

Rapid evaluation of a coal resource by in-situ characterisation dow...

C34028Guidelines For Assessment Of Geotechnically Safe And Stable Post-Mining Landforms

The purpose of this project was to develop a guidelines document as ...

C34016Elements In Coal – A Start-To-End Analysis

This project explores the fate and concentration potential of critical e...

Open Cut

Coal Preparation

Maximising throughput and yield while minimising costs and emissions.

Recently Completed Projects

C26016Determining The Benefits Of Online Thickener Underflow Rheology Measurements

The aim of this project is to determine how useful the rheology meas...

C33056Modelling And Control Of Classifying Cyclones

Hydrocyclones are one of the key technologies for the classification...

C28056Surface Alloying Of Centrifuge Baskets And Sieve Bends Screen Surfaces To Increase The Service Lifetime

The main objective of this project was to improve the wear resistanc...

Coal Preparation

Technical Market Support

Market acceptance and emphasising the advantages of Australian coals.

Recently Completed Projects

C33066Washability And Distribution Of Sulfur And Trace Elements For Different Size And Density Fractions Of Raw Coals

Based on the hypothesis that the levels of sulfur and other toxic tr...

C34060In-Situ Investigation Of Coke Structure Formation Under Stamp Charged Coking Conditions

Stamp charged cokemaking has emerged as an effective technique to im...

C34062Improving The Classification Of Microstructure Distribution In Coke CT Images Using Deep Learning And Lineal Path Calculations

This project builds on a number of earlier projects that have helped...

Technical Market Support

Mine Site Greenhouse Gas Mitigation

Mitigating greenhouse gas emissions from the production of coal.

Recently Completed Projects

C28076Selective Absorption Of Methane By Ionic Liquids (SAMIL)

This third and final stage of this project was the culmination of a ...

C29069Low-Cost Catalyst Materials For Effective VAM Catalytic Oxidation

Application of ventilation air methane (VAM) thermal oxidiser requir...

C23052Novel Stone Dust Looping Process For Ventilation Air Methane Abatement

This multi‐phase project is concerned with the mitigation of m...

Mine Site Greenhouse Gas Mitigation

Low Emission Coal Use

Step-change technologies aimed at reducing greenhouse gas emissions.

Recently Completed Projects

C17060BGasification Of Australian Coals

Four Australian coals were trialled in the Siemens 5 MWth pilot scale ga...

C17060AOxyfuel Technology For Carbon Capture And Storage Critical Clean Coal Technology - Interim Support

The status of oxy-fuel technology for first-generation plant is indicate...

C18007Review Of Underground Coal Gasification

This report consists of a broad review of underground coal gasification,...

Low Emission Coal Use

Mining And The Community

The relationship between mines and the local community.

Recently Completed Projects

C16027Assessing Housing And Labour Market Impacts Of Mining Developments In Bowen Basin Communities

The focus of this ACARP-funded project has been to identify a number...

C22029Understanding And Managing Cumulative Impacts Of Coal Mining And Other Land Uses In Regions With Diversified Economies

The coal industry operates in the context of competing land-uses that sh...

C23016Approval And Planning Assessment Of Black Coal Mines In NSW And Qld: A Review Of Economic Assessment Techniques

This reports on issues surrounding economic assessment and analysis ...

Mining And The Community

NERDDC

National Energy Research,Development & Demonstration Council (NERDDC) reports - pre 1992.

Recently Completed Projects

1609-C1609Self Heating of Spoil Piles from Open Cut Coal Mines

Self Heating of Spoil Piles from Open Cut Coal Mines

1301-C1301Stress Control Methods for Optimised Development...

Stress Control Methods for Optimised Development and Extraction Operations

0033-C1356Commissioned Report: Australian Thermal Coals...

Commissioned Report: Australian Thermal Coals - An Industry Handbook

NERDDC