Dragline Automation System: Optimal Excavation Sequencing

Open Cut » Overburden Removal

Published: September 15Project Number: C23033

Get ReportAuthor: Kevin Austin, Matthew Green, Ross McAree | The University of Queensland

Dragline excavation sequencing describes the complex problem of determining the sequence of tub positions and the associated material movement task for each tub position for dragline strip mining. This project has examined computational methods for computing excavation sequences. It is thought that these methods can be the base for an operator decision support that instructs the operator where to position, what material to take, when to move, and where to move to.

 

The project has been conducted by the Smart Machines Group at The University of Queensland and the SME Mineware. This report describes the progress made and identifies a pathway toward commercialization.

 

The methodology of the study has been to:

· Understand the requirements of an operator assist for excavation sequencing from the perspective of dragline operators, supervisors, and engineers;

· Characterize the decision making processes for excavation to understand the functional elements of the sequencing problem and how they interrelate, and to identify sub-problems that can be solved;

· Develop a software framework for providing the functional capabilities of excavation sequencing;

· Apply identified strategies to address excavation sequencing for a steady state excavation scenario and make comparisons with actual operation.

 

Dragline excavation sequencing is a complex problem. There are many factors that influence the decision to excavate material from a particular position: the volume of material that can be reached and how the volume is distributed; the efficiency of digging the reachable material; the average cycle time for moving the material to spoil; the available spoil room and how the available room is distributed; and the impact of future excavation requirements. These factors result in a large decision space with competing objectives and constraints. The approach taken for this project was to impose structure to the excavation task through the prescription of material assignment to a position (i.e. layered excavation strategy describing target profiles for the block walk-up sequence), prescribing an order of material removal, and applying a front-to-back spoiling strategy to minimize swing angle. These strategies were considered appropriate for the test strip and could be augmented to include strategies appropriate for other strip geometries.

 

The imposed structure for the block excavation represents a template for excavation based on actual execution (e.g. percentage of block volume removed at each walk up position, block length, block shape) and established strategies for removing material to spoil. This structure reduces the dimensionality of the decision making process to one that seeks to identify the walk-up positions that will maximize the lineal advance of the strip.

 

The excavation sequencing algorithm developed has been applied to data collected from Dragline 17 at BMA's Peak Downs site. A strip was chosen to provide a steady state operation for approximately 200m of lineal advance. In this section there were no ramps, corners or discontinuities in the target profile. This allowed several complexities of general operation to be marginalized. The dragline was operating on an in-pit bench, initially constructed from an extended key process. The overall excavation task was to excavate the bench and residual material left in the key.

 

The algorithm was compared in its performance to operators and out-performed them. Not surprisingly operators will make different decisions based on experience / prejudices and the quality of their perception of the required current and future material movements. To arrive at a decision requires trading off various objectives and constraints.

 

For the test strip the operator cycle data shows a mean swing angle of 85 degrees with a mean cycle time of 73 seconds. The swing angles recorded ranged from 10 degrees up to 200 degrees with a standard deviation of 32.5 degrees. The source of this variation is unknown but it is suggested that the variation is typical of what might be expected from multiple operators across different shifts. When the algorithm was applied to the same data the mean cycle time was reduced to 51 seconds.

 

An attribute of effective sequencing is better utilization of spoil. The computed solutions both produce spoil that sits against the design spoil shell representing minimum movement of material. If a decision support tool were able to sufficiently guide operators to deliver better sequencing it is estimated that an overall 10% productivity improvement could be achieved. Sensitivity analysis showed that a further 10% productivity improvement could be achieved by moving from a 15m to 25m blocks.

 

A planned Phase 2 of this work will verify the value proposition and augment the existing dragline sequencing capabilities by extending the ideas and deploying to a production dragline for evaluation.

Underground

Health and safety, productivity and environment initiatives.

Underground

Open Cut

Safety, productivity and the right to operate are priorities for open cut mine research.

Recently Completed Projects

C19024Establishing Ecologically Sustainable Mine Water Release Criteria In Seasonally Flowing Streams

Extreme rainfall conditions in the Fitzroy Catchment over an approxi...

C25030Coal Mine Open Pit Final Void Closure And Relinquishment - Addressing Uncertainty In Coal Mine Environmental Planning

This report addresses uncertainties faced by coal mine operators whe...

C27046Estimation Of True Deformation Vector From Slope Radar Monitoring

Slope deformation radar monitors are now widely used in open cut coa...

Open Cut

Coal Preparation

Maximising throughput and yield while minimising costs and emissions.

Recently Completed Projects

C27004Improving Coal Flotation With Oscillatory Air Supply

This report provides detailed information on coal flotation with os...

C25018Improving Solids Recovery And Moisture Reduction In Ultrafine Coal Dewatering

This report provides detailed information on fine coal dewatering in...

C27028Lab Froth Flotation Testing Guide With Coal Quality

Correct outcomes from laboratory froth flotation testing in coal bor...

Coal Preparation

Technical Market Support

Market acceptance and emphasising the advantages of Australian coals.

Recently Completed Projects

C26039Nanoporosity In Cokes: Their Origin, Control And Influence On CO2 Reactivity

This project using the outcomes of previous project C24060, examine...

C28063A Comprehensive Technical Review Of High-Efficiency Low-Emission (HELE) Pulverised Coal Combustion Technologies For Power Generation

Research and development has been undertaken worldwide to realise co...

C28064Carbon Structure Transformation During Coking Of Australian Coking Coals: Better Understanding The Coke Formation

Carbon structures of coke that are formed during the plastic layer a...

Technical Market Support

Mine Site Greenhouse Gas Mitigation

Mitigating greenhouse gas emissions from the production of coal.

Recently Completed Projects

C28076Selective Absorption Of Methane By Ionic Liquids (SAMIL) - Phase 2 Demonstration In A Packed Bed Reactor

An alternative approach to high temperature oxidation of ventilation...

C26004CFD Modelling Of Reverse Thermal Oxidisers For VAM Abatement - CFD Modelling Of Fixed-Bed RTO Devices

The project is part of a larger multi‐phase program of study a...

C27058Technological Assessment Of A Recycle Reactor For VAM Abatement

Underground coal mining emits high volumes of methane, diluted in ve...

Mine Site Greenhouse Gas Mitigation

Low Emission Coal Use

Step-change technologies aimed at reducing greenhouse gas emissions.

Recently Completed Projects

C17060BGasification Of Australian Coals

Four Australian coals were trialled in the Siemens 5 MWth pilot scale ga...

C17060AOxyfuel Technology For Carbon Capture And Storage Critical Clean Coal Technology - Interim Support

The status of oxy-fuel technology for first-generation plant is indicate...

C18007Review Of Underground Coal Gasification

This report consists of a broad review of underground coal gasification,...

Low Emission Coal Use

Mining And The Community

The relationship between mines and the local community.

Recently Completed Projects

C16027Assessing Housing And Labour Market Impacts Of Mining Developments In Bowen Basin Communities

The focus of this ACARP-funded project has been to identify a number...

C22029Understanding And Managing Cumulative Impacts Of Coal Mining And Other Land Uses In Regions With Diversified Economies

The coal industry operates in the context of competing land-uses that sh...

C23016Approval And Planning Assessment Of Black Coal Mines In NSW And Qld: A Review Of Economic Assessment Techniques

This reports on issues surrounding economic assessment and analysis ...

Mining And The Community

NERDDC

National Energy Research,Development & Demonstration Council (NERDDC) reports - pre 1992.

Recently Completed Projects

1609-C1609Self Heating of Spoil Piles from Open Cut Coal Mines

Self Heating of Spoil Piles from Open Cut Coal Mines

1301-C1301Stress Control Methods for Optimised Development...

Stress Control Methods for Optimised Development and Extraction Operations

0033-C1356Commissioned Report: Australian Thermal Coals...

Commissioned Report: Australian Thermal Coals - An Industry Handbook

NERDDC