ACARP ACARP ACARP ACARP
Open Cut

Stress Relieving and Pre-Fabricated Nodes for BE Dragline Booms

Open Cut » Maintenance & Equipment

Published: August 05Project Number: C13045

Get ReportAuthor: Daya Dayawansa, Brian Kerezsi, John Price, Ana Paradowska | MTI, Monash University

A previous ACARP project (C11052) identified weld quality and residual stresses as two major factors contributing to poor fatigue life of BE boom clusters compared to Marion clusters. The traditional fabrication methods that have been used for decades without much improvement are responsible for both these factors. Surprisingly, according to the current practice, the main chord butt welds that have comparatively more favourable conditions from residual stress and weld quality view points are stress relieved, while the clusters that generate more than 90% of fatigue problems are not stress relieved. Stress relieving is expected to improve fatigue life of clusters significantly, and as part of this project sound procedures for cluster stress relieving have been developed and successfully trialled on a BE boom.

Stress relieving in-situ can have other effects such as structural deformations, material property changes, etc. These effects were comprehensively examined though the laboratory and field trials undertaken as part of the project. The results indicate that stress relieving of BE boom clusters can be undertaken safely to improve the fatigue performance of the clusters. 

The investigations found that stress relieving also had other benefits such as tempering the weld material and also reducing the hardness of welds. These improvements will also contribute to improving the resistance to initial growth of cracks under load by improving the toughness of the steel near the welds. 

The following specific conclusions were made from the cluster stress relieving investigation:

  • Stress relieving can significantly reduce the unfavourable axial tensile residual stresses in a cluster. Following the recommended procedure in the report, the residual stress levels can be reduced at least by 40%.
  • Stress relieving the clusters as recommended can increase the fatigue life of clusters at least by 50% and possibly up to 100%. 
  • The cost of stress relieving a pair of clusters (i.e. A and B chords) varied between $3-5k. During the field trials at Blackwater mine, stress relieving of six pairs of clusters were undertaken with no addition to the overall shutdown duration.
  • Stress relieving also has a beneficial effect on the hardness of welds, reducing them to acceptable levels. This will also contribute to longer fatigue life of clusters.
  • The procedure adopted for stress relieving of clusters generally conforms to AWS D1.1:2000 Structural Welding Code – Steel [6].
  • The adopted stress relieving procedure has no significant influence on the microstructure of the steel used in the boom. The material tests showed that the influence of stress relieving on the other material properties such as the yield strength of the parent material is small, and therefore should not significantly affect the strength of the boom.
  • Based on the findings of the investigation, stress relieving of clusters is recommended for all new clusters in BE booms.

When clusters are replaced after several repairs, the conventional approach is to cut off ~2m length of main chord covering the cluster and replace it with a new main chord segment, and then weld all the lacing pups in-situ to complete the cluster. This approach results in poor weld quality and high levels of residual stresses, and also contributes to longer shutdown durations. Using the latest techniques in surveying and accurate fabrication methods, it is possible to prefabricate the clusters under shop conditions, stress relieve them under controlled conditions, and complete only the attachment welds under field conditions at less critical locations.

The project investigated the feasibility of pre-fabricating the clusters with higher weld quality standards, stress relieving them under well controlled conditions and then attaching them to the booms during shutdowns.  This procedure can reduce the downtime of the machines and also significantly improve the fabrication quality of the clusters. The investigation concluded that the pre-fabrication of clusters is technically feasible to implement on a dragline boom.  However, a field trial could not be undertaken as an opportunity to implement it on an actual dragline boom could not be found. Some of the measuring techniques were trialed on a cluster manufactured in the laboratory.  

Underground

Health and safety, productivity and environment initiatives.

Recently Completed Projects

C33029Review Longwall Face Ventilation To Mitigate Goaf Gas Emissions Onto Walkways And Tailgate End

As longwall mining increasingly targets deeper coal seams, managing ...

C29009Control Of Transient Touch Voltages During Switching

There have been an increasing number of electric shock incidents rep...

C29025Effectiveness Of Shotcrete In Underground Coal Mines

The primary objective of this project is to quantify the effectivene...

Underground

Open Cut

Safety, productivity and the right to operate are priorities for open cut mine research.

Open Cut

Coal Preparation

Maximising throughput and yield while minimising costs and emissions.

Recently Completed Projects

C33057Foreign Contaminants Detection On Conveyor Belts Using Digital Imaging Processing Techniques And Coal Penetrating Sensors

This project was initiated to tackle the ongoing issue of foreign co...

C29061Improving Flotation With A Combined Method

This project aimed to develop and assess a method combining the use ...

C33053Improving Centrifugal Dewatering Via Modelling And Analysis

The aim of the project was to develop a model for screen bowl centri...

Coal Preparation

Technical Market Support

Market acceptance and emphasising the advantages of Australian coals.

Recently Completed Projects

C34059Coke Reactivity With CO2 And H2O And Impacts On Coke Microstructure And Gas Diffusion

With the global shift to low-carbon ironmaking, partial substitution...

C34055Factors Underpinning The Gasification Reactivity Of Coke RMDC And IMDC With CO2

It is well known that the gasification reactivity of metallurgical c...

C33066Washability And Distribution Of Sulfur And Trace Elements For Different Size And Density Fractions Of Raw Coals

Based on the hypothesis that the levels of sulfur and other toxic tr...

Technical Market Support

Mine Site Greenhouse Gas Mitigation

Mitigating greenhouse gas emissions from the production of coal.

Recently Completed Projects

C34066Safe Operation Of Catalytic Reactors For The Oxidation Of VAM Operating Under Abnormal Reaction Conditions

The catalyst Pd/TS-1 has shown excellent activity in oxidising venti...

C28076Selective Absorption Of Methane By Ionic Liquids (SAMIL)

This third and final stage of this project was the culmination of a ...

C29069Low-Cost Catalyst Materials For Effective VAM Catalytic Oxidation

Application of ventilation air methane (VAM) thermal oxidiser requir...

Mine Site Greenhouse Gas Mitigation

Low Emission Coal Use

Step-change technologies aimed at reducing greenhouse gas emissions.

Recently Completed Projects

C17060BGasification Of Australian Coals

Four Australian coals were trialled in the Siemens 5 MWth pilot scale ga...

C17060AOxyfuel Technology For Carbon Capture And Storage Critical Clean Coal Technology - Interim Support

The status of oxy-fuel technology for first-generation plant is indicate...

C18007Review Of Underground Coal Gasification

This report consists of a broad review of underground coal gasification,...

Low Emission Coal Use

Mining And The Community

The relationship between mines and the local community.

Recently Completed Projects

C16027Assessing Housing And Labour Market Impacts Of Mining Developments In Bowen Basin Communities

The focus of this ACARP-funded project has been to identify a number...

C22029Understanding And Managing Cumulative Impacts Of Coal Mining And Other Land Uses In Regions With Diversified Economies

The coal industry operates in the context of competing land-uses that sh...

C23016Approval And Planning Assessment Of Black Coal Mines In NSW And Qld: A Review Of Economic Assessment Techniques

This reports on issues surrounding economic assessment and analysis ...

Mining And The Community

NERDDC

National Energy Research,Development & Demonstration Council (NERDDC) reports - pre 1992.

Recently Completed Projects

1609-C1609Self Heating of Spoil Piles from Open Cut Coal Mines

Self Heating of Spoil Piles from Open Cut Coal Mines

1301-C1301Stress Control Methods for Optimised Development...

Stress Control Methods for Optimised Development and Extraction Operations

0033-C1356Commissioned Report: Australian Thermal Coals...

Commissioned Report: Australian Thermal Coals - An Industry Handbook

NERDDC