ACARP ACARP ACARP ACARP
Open Cut

Improved Dragline Spoiling Through 3D Simulation

Open Cut » Overburden Removal

Published: July 94Project Number: C3037

Get ReportAuthor: Murray Phillips | ACIRL

The objectives of this project were:

  • To conduct a field study at Peak Downs Mine to acquire the following data on the excavation of a typical block:
  • Calibrated stereo pair photographs to produce digital terrain models (DTM's) of key stages of the operation

Detailed productivity data including swing counts

  • To use the above data to quantify the volumetric and productivity parameters associated with the observed block.
  • To use the above information to calibrate 3d-Dig and simulate the excavation of the observed block.
  • To set up a model of the complete pit where the standard operating method will result in the dragline being spoil bound, and to study the following alternative strategies:
  • Truck shovel pre-strip to remove excess spoil

Dragline spoil pull back to create additional spoil room to accommodate excess spoil

The use of a dragline hopper truck system to remove excess spoil during the second pass operation

RESULTS

The stereo pair photographs were successfully digitised to produce DTM's. The technique is recommended for dragline studies subject to the following cautions:

  • Very large control targets must be used. In this study the size of targets used in the spoil were about 700mm square. This size is barely adequate. We would recommend targets of about 1.5m square
  • At least 4 targets must be visible in each photograph. Furthermore these must be distributed roughly evenly about the region of interest. Two targets in close proximity may induce errors or result in the inability to orient the photographs. Such problems are best avoided by installing an excess of targets, rather than the minimum.
  • When photographing a stereo pair care must be taken to ensure the orienting of the camera axis is approximately the same for both photographs. If there is much divergence it may not be possible to bring them into stereo view when processing. A compass and inclinometer should be adequate for this purpose.

Wherever practical we recommend the use of a light aircraft to acquire aerial photographs. This will avoid most of the problems alluded to above. Furthermore the entire operation can be digitised from just one pair. Using land based photography between 3 and 4 pairs will be required, with subsequently much greater processing time required to digitise. Aerial photography will generally prove to be more accurate and cost effective.

3d-Dig was successfully calibrated and used to simulate the observed block. The block was divided into two sub operations,

  • spoil dumping and
  • bridge building.

The results were:

Operation Observed

(BCM/op hr)

Simulated

(BCM/op hr)

Correction

factor

 
spoil dumping 1779 1825 0.97
key/bridge 1835 1976 0.928

The difference between the observed and simulated has been used as a correction factor within 3d-Dig for subsequent simulation. An over estimate of productivity is to be expected as the modelling cannot take account of all operational inefficiencies.

The volumes associated with full strip modelling were:

  • First Pass 2,970,000 BCM, area of coal uncovered 66,264m3
  • Total 4,820,000 BCM, area of coal uncovered 7,4910m3
  • Excess spoil 1,080,000 BCM (included in total above)

All three auxiliary stripping strategies were found to be feasible.

The production statistics are:

Pre-Strip Option

Total volume trucked 1080000 BCM

Total truck hours 2823

Total truck kilometres 61780

Dragline stripping

Total blasted prime 3740000 BCM

First pass dragline stripping:

  • Total operating time 797hrs
  • Total volume 1391000 BCM
  • Rehandle 5800 BCM
  • Overall productivity 1745 BCM/op hr

Second pass stripping:

  • Total operating time 2707 hrs
  • Total volume 4570000 BCM
  • Rehandle 2356000 BCM

Overall productivity 1686 BCM/op hr

Dragline Pullback Option

Total volume 1210000 BCM

Total operating time 731 hours

Overall productivity 1662m3/op hr

Coal uncovery operation

Blasted prime 4820000 BCM

First pass:

  • Total volume 2228800 BCM
  • Rehandle 5000 BCM
  • Total operating time 1350 hrs
  • Overall productivity 1650m3/op hr

Second pass:

  • Total volume 5152000 BCM
  • Rehandle 2870000 BCM
  • Total operating time 3220 hrs
  • Overall productivity 1600 BCM/op hr

Dragline Hopper Truck Option

Total truck hours 2488

Total truck kilometres 55105

Dragline operation first pass

  • Total volume 2230000 BCM
  • Volume to hopper 1080000 BCM
  • Total dragline hours 1423
  • Overall productivity 1567m3/op hr

Dragline second pass as for pre-strip option

The interaction between the dragline and the hopper truck system is a complex one. Due to the lack of information on the stochastic variables associated with the operation of such a system, a somewhat rudimentary analysis has been conducted here. For more detailed knowledge it is recommended that as such data becomes available it should be used to build a more detailed model.

It would be feasible to build a model of the hopper truck system within 3d-Dig and have the system model all aspects of the interacting systems. This would lead to more accurate modelling, particularly in regards to the effect of equipment availability.

3d-Dig

3d-Dig is an integrated excavation design, dump design and dragline simulation system. It provides full 3d modelling of all aspects of the dragline operation. The system imports and honours all relevant data on the existing pit topography, coal seams and machine parameters. 3d-Dig presents the user with a perspective view of the topography, via a straight forward mouse driven interface the dragline can be placed and an excavation performed. The user can save data files and hardcopies for each step of the operation, providing 'replay' of the digging sequence and allowing a new analysis to commence at any point.

Modelling Methodology

3d-Dig works by taking a Digital Terrain Model (DTM) of the existing pit. It then removes user designed bodies of spoil to simulate excavation, the DTM is modified to reflect this change and the material is swelled and stored to a material buffer. The user can then define an area within which to dump this material (typically somewhere within a dragline's dump radius, for dragline excavation). The material within the buffer is then numerically dumped, in discrete parcels, onto spoil and the topography is modelled and the resultant topography determined. This process continues until all material in the buffer is placed. 3d-Dig also models the movements required to perform the dragline operation and so calculates productivity. The functionality has been implemented in a flexible manner which also allows for the study of non-dragline systems (bucket wheel, truck shovel etc).

In order to fully model a three dimensional pit operation 3d-Dig must import and maintain a large body of data. Broadly this includes:

  • Digital terrain model (DTM) of existing pit
  • DTM of design topography
  • Coal seam model
  • Spoil characteristics (repose angle, specific gravity and swell factor)
  • Machine parameters (geometry and performance characteristics)
  • Performance log (volumes moved, productivity rates machine movement)

 

Underground

Health and safety, productivity and environment initiatives.

Recently Completed Projects

C34019Longwall Bretby Cable Handling Monitoring With Fibre Optics

This project examined the potential of using fibre optic sensing tec...

C27049Mine Machine Radar Sensor Integration

The aim of this project was to develop an integrated radar sensor an...

C29007Innovative Coal Burst System To Investigate The Influence Of Confinement Loss And Pre-Conditioning On Coal Burst Mechanism

The challenges associated with designing and operating a safe and pr...

Underground

Open Cut

Safety, productivity and the right to operate are priorities for open cut mine research.

Recently Completed Projects

C33035High Water Recovery, Low Cost Desalination Using PV-Powered Membrane Capacitive Deionisation (Mcdi)

Capacitive deionization is a robust, energy efficient and cost effec...

C28035Topsoil Deficits In Site Rehabilitation Accelerated Transformation Of Spoils To Functional Soils

The incorporation of commercial biological amendments (compost, worm...

C34036Tyre Handler Testing Rig Stage 2: Lifting Trials

Tyre handling is a major source of risk in surface mining operations...

Open Cut

Coal Preparation

Maximising throughput and yield while minimising costs and emissions.

Coal Preparation

Technical Market Support

Market acceptance and emphasising the advantages of Australian coals.

Recently Completed Projects

C34060In-Situ Investigation Of Coke Structure Formation Under Stamp Charged Coking Conditions

Stamp charged cokemaking has emerged as an effective technique to im...

C34062Improving The Classification Of Microstructure Distribution In Coke CT Images Using Deep Learning And Lineal Path Calculations

This project builds on a number of earlier projects that have helped...

C29071Source Of Variability Of Reactivity Of Coke In The CSR Test

The Coke Strength after Reaction (CSR) test is used worldwide to det...

Technical Market Support

Mine Site Greenhouse Gas Mitigation

Mitigating greenhouse gas emissions from the production of coal.

Recently Completed Projects

C28076Selective Absorption Of Methane By Ionic Liquids (SAMIL)

This third and final stage of this project was the culmination of a ...

C29069Low-Cost Catalyst Materials For Effective VAM Catalytic Oxidation

Application of ventilation air methane (VAM) thermal oxidiser requir...

C23052Novel Stone Dust Looping Process For Ventilation Air Methane Abatement

This multi‐phase project is concerned with the mitigation of m...

Mine Site Greenhouse Gas Mitigation

Low Emission Coal Use

Step-change technologies aimed at reducing greenhouse gas emissions.

Recently Completed Projects

C17060BGasification Of Australian Coals

Four Australian coals were trialled in the Siemens 5 MWth pilot scale ga...

C17060AOxyfuel Technology For Carbon Capture And Storage Critical Clean Coal Technology - Interim Support

The status of oxy-fuel technology for first-generation plant is indicate...

C18007Review Of Underground Coal Gasification

This report consists of a broad review of underground coal gasification,...

Low Emission Coal Use

Mining And The Community

The relationship between mines and the local community.

Recently Completed Projects

C16027Assessing Housing And Labour Market Impacts Of Mining Developments In Bowen Basin Communities

The focus of this ACARP-funded project has been to identify a number...

C22029Understanding And Managing Cumulative Impacts Of Coal Mining And Other Land Uses In Regions With Diversified Economies

The coal industry operates in the context of competing land-uses that sh...

C23016Approval And Planning Assessment Of Black Coal Mines In NSW And Qld: A Review Of Economic Assessment Techniques

This reports on issues surrounding economic assessment and analysis ...

Mining And The Community

NERDDC

National Energy Research,Development & Demonstration Council (NERDDC) reports - pre 1992.

Recently Completed Projects

1609-C1609Self Heating of Spoil Piles from Open Cut Coal Mines

Self Heating of Spoil Piles from Open Cut Coal Mines

1301-C1301Stress Control Methods for Optimised Development...

Stress Control Methods for Optimised Development and Extraction Operations

0033-C1356Commissioned Report: Australian Thermal Coals...

Commissioned Report: Australian Thermal Coals - An Industry Handbook

NERDDC